Parramatta Stadium Master Plan - 2011
In 2010 the Parramatta
Stadium Trust commissioned Hassell architects to review the existing master
plan of the stadium and make recommendations as to the development of the
venue.
The concept plan has been
adopted by the Trust and stakeholders have been engaged in preparing a business
case for the development.
It should be noted that the
whole landscape of the precinct East of The Parramatta River has been included
and of course consultation with the Parramatta Park Trust is essential and has
already commenced.
The Master Plan takes into
account future requirements for the venue to maintain market position in
providing first rate facilities for patrons and players, attracting new hirers
( players and corporate facilities) and creating additional revenue opportunity
(function facility) in order to retain self funding status for operations and
minor works.
The facts of the development
are as follows:-
Stage 1 A –
C Upgrade
the Eastern and Western Grandstands and install extra 3,300 sets on the Earth
Mounds (North and South) including identifiable unique façade (screen or ‘skin’).
Benefit: 1. Eastern Grandstand
500 Seat Function room (Can be sectioned for varying
capacities)
650 more corporate patrons catered
for in corporate
suites at the top of the grandstand
Catering outlets improved
2. Western
Grandstand
Players
facilities significantly improved – four dressing rooms and 2 gymnasiums for
additional hirers at an international standard
Catering outlets improved
Provision of office space for the Trust and other
users
Increased capacity of the stadium to
23,500
Stage 2 Public
Domain Upgrade and Landscaping
Benefit: 1.
Pedestrian access along
widening)
2. Vastly improved patron circulation
around the venue via
suspended concourse behind the Eastern Grandstand
3. Creation of Northern and Southern entry
plazas
4. Patron approaches from the south from
the train station
via CBD is
accentuated
Stage 3 Park
Precinct Works
Benefit:
These
works require Park Trust involvement and the benefit is the inclusion of the
stadium into the landscape of the park and improved pedestrian flows around the
precinct.
Stage 4
& 5 Northern
and Southern Spectator Stands
Benefit: Increased
public capacity of the venue to 31,300